This retail outlet shopping mall had 525,000 square
feet of roof. The project presented a multitude of challenges,
including 18 different roof sections, with several levels, half
completed walls, partial curb installation, difficulties in loading
inside buildings, winter weather, and very tight deadlines which were
always in jeopardy due to multiple trades working at the same time.
Anthony’s
use of a thermoplastic roof system over metal decking guaranteed the
best life cycle costs and overall value for the owner.
The project was completed on time, within budget, and in compliance with its usual stringent safety standards.
|